The A41 flyover contraflow is listed to 20 November and one westbound A406 lane stays shut until 13 November, plus other Barnet works. Updated November 2026.

Brent Cross is still the Barnet roadworks to plan around, and the layout changed again this morning. The A41 Hendon Way flyover now runs as a contraflow, one lane each way. TfL’s live feed, updated at 11.14pm on Monday 2 November, says the contraflow “is in place”. TfL lists the flyover works to 6pm on Friday 20 November.

Lane one of the westbound A406 North Circular stays shut from Golders Green Road until 5am on Friday 13 November, and the eastbound A406 exit slip is down to one lane of two.

New this week: gas works on Hendon Way at Cricklewood Lane. TfL’s feed lists a northbound lane restriction on the A41 at its junction with the A407 Cricklewood Lane for Cadent gas works. It started at 5.45pm on Monday 2 November and is listed to 6pm on Monday 9 November.

Five Hendon side roads off Great North Way shut overnight, 10pm to 5.30am, for urgent M1 investigation works, which began on Monday 2 November: Sunny Gardens and Chatsworth Avenue for 13 nights, Ashley Lane, Downage and Westside for three. On the same three nights National Highways shuts the A1 Great North Way entry slip to the M1 northbound at junction 2, and TfL’s feed had the A1 Great North Way northbound closed overnight between Parson Street and Hilltop Gardens for highway works (details below).

The A411 Barnet Road closure at Glebe Lane, Arkley, has dropped off TfL’s feed. It was listed to the end of Thursday 5 November for Thames Water works. TfL has not said whether the road has reopened early, so we cannot confirm it is clear.

The Elliot Road lane closures on northbound Hendon Way, listed to 1 November, are no longer on the feed. In North Finchley, Lodge Lane and Gainsborough Road gained no-entry restrictions on 29 October, and Gainsborough Road and Netherfield Road stay closed to about 21 November.

This page is rewritten each time we check the sources. TfL’s live road feed was re-read early on 3 November. TfL’s travel advice for the flyover, every Barnet notice on the Public Notice Portal, National Highways’ closure report, TfL’s planned closures and National Rail were last read in full on 31 October.

Updated 3 November: the contraflow is now in place; Cadent gas works added on Hendon Way at Cricklewood Lane; the A411 Glebe Lane closure is no longer on TfL’s feed.

Last checked 3 November 2026.

Brent Cross roadworks: what is shut and when

When What is shut at Brent Cross
Now, to 5am Friday 13 November Lane one of the westbound A406 shut from Golders Green Road
Now, to 6pm Friday 20 November Contraflow on the A41 Hendon Way flyover, one lane each way (from 3 November)
Thu 12 and Fri 13 November, 10pm to 5am A406 westbound between the interchange slips; traffic goes up and over
Thu 19 and Fri 20 November, 10pm to 5am A41 Hendon Way, both directions, between Vivian Avenue and The Vale
Late November to early January Works paused for Christmas
4 to 12 January 2027, nights Hendon Way shut on 4 and 5 January; the A406 beneath the interchange on 6, 7, 8, 11 and 12 January

The Brent Cross footbridge is closed for repairs as well, TfL’s travel advice says.

The A406 North Circular approaching Brent Cross, with 'Brent Cross' painted on the carriageway and traffic in the far lanes
The A406 North Circular approaching Brent Cross. Photo: Stacey Harris (CC BY-SA 2.0), via Wikimedia Commons

Brent Cross flyover: the dates in full

The Brent Cross flyover carrying Hendon Way over the North Circular, with a curving slip road below it
Hendon Way crossing the North Circular on the Brent Cross flyover. Photo: David Howard (CC0), via Wikimedia Commons

The contraflow is now running. TfL’s live feed (record updated 11.14pm on Monday 2 November) says: “Until 18:00 Friday 30 November, a contraflow on A41 Hendon Way flyover is in place.” 30 November is a Monday, not a Friday, and the same record gives its own end as 6pm on Friday 20 November, so we read the end as 20 November until TfL corrects it.

TfL’s travel advice for the works, last read on 31 October, said the contraflow would start on 29 October. The feed moved that to 7am on Tuesday 3 November.

We work to the feed, which is the newer record and the one TfL’s traffic status page draws on (TfL traffic status). Whether the overnight Hendon Way closures of 29 and 30 October went ahead as planned, neither source says.

The overnight closures still to come, each from 10pm to 5am:

Night Closed
Thursday 12 and Friday 13 November A406 westbound, between the interchange exit and entry slips. Traffic goes up and over the interchange
Thursday 19 and Friday 20 November A41 Hendon Way, both directions, between Vivian Avenue and The Vale
Monday 4 and Tuesday 5 January 2027 A41 Hendon Way, both directions, between Vivian Avenue and The Vale
Wednesday 6, Thursday 7, Friday 8, Monday 11 and Tuesday 12 January 2027 A406 North Circular, both directions, beneath Brent Cross Interchange, for concrete repairs

TfL says there will be signed diversions for all closures and that “some bus routes will be diverted” during the overnight Hendon Way closures, with some stops on or near Hendon Way not served. It does not name the routes for the November nights. It also says more overnight closures may be needed and that it will share dates once confirmed.

The project page says work will pause “from late November 2026 to early January 2027” and continue for up to two years in all. The job is to strengthen the flyover, replace its safety barriers and waterproof it, so that the 7.5-tonne weight restriction in place since October 2022 can come off at the end. The Department for Transport has put in £10.8 million. We set out the full story in our report on the flyover works.

The other works on TfL’s feed

TfL’s feed carried three Barnet entries early on 3 November: the Brent Cross flyover, the Cadent gas works on Hendon Way at Cricklewood Lane (northbound, to 6pm on 9 November) and an overnight A1 Great North Way closure. On 31 October and 1 November it carried these three:

  • A41 Brent Cross flyover renewals, as above.
  • A411 Barnet Road at the junction of Glebe Lane, Arkley (EN5): a road closure, both directions, for Thames Water works, listed from 2.30pm on Monday 19 October to the end of Thursday 5 November. TfL says to use an alternative route and that delays are possible on the diversion.
  • A41 Hendon Way northbound at Elliot Road (NW4): lanes one and two of three closed for emergency Thames Water works, listed from 5pm on Wednesday 28 October to the end of Sunday 1 November. TfL reported no delays on the diversion.

The A5 Edgware lane restrictions at Spring Villa Road and the broken pedestrian lights on the A406 Pinkham Way at Station Road, both listed on 20 October, are no longer on the feed. There are no TfL entries for Apex Corner, the A1 Watford Way, Barnet Way or the A5 through Colindale.

Hendon M1 night closures

Barnet Council made five closure orders on 29 October “to facilitate access for urgent investigation works to be carried out on the M1”. Each closure runs from the road’s junction with Great North Way, between 10pm and 5.30am, from Monday 2 November:

Road Length closed Nights Diversion Contingency dates
Sunny Gardens NW4 16.4 metres south from Great North Way 13 Watford Way, Greyhound Hill and Church Road 23 to 25 November
Chatsworth Avenue NW4 15.3 metres south from Great North Way 13 Watford Way, Greyhound Hill and Church Road 23 to 26 November
Ashley Lane NW4 18.6 metres south from Great North Way 3 B552 Parson Street, A504 Finchley Lane, A1, A406 eastbound, A1000, A406 westbound 1 to 3 December
Downage NW4 16.4 metres south from Great North Way 3 The same route; the notice spells the A504 as “Finchley Road” 1 to 3 December
Westside NW4 From Great North Way 3 The south-western side of Westside 1 to 3 December

The contingency dates only apply if the works are not finished on schedule. The north-eastern footpath of Colin Crescent NW4, between Colin Crescent and Endersleigh Gardens, also closes for one day from Monday 2 November for investigation works; walk via Endersleigh Gardens, Grove Gardens and Colindeep Lane.

National Highways’ closure report separately books the A1 Great North Way entry slip road to the M1 northbound at junction 2 shut on the nights of Monday 2, Tuesday 3 and Wednesday 4 November, 10pm to 5.30am, for “carriageway repair works”. Neither the council nor National Highways says whether the two jobs are linked (the Sunny Gardens order, Chatsworth Avenue, Ashley Lane, Downage, Westside, Colin Crescent).

What is restricted right now on council roads

These orders were read in full on the Public Notice Portal between 16 and 31 October, and all were still listed there on 31 October. The end dates are the council’s.

  • Gainsborough Road and Netherfield Road, Woodside Park (N12): closed to about 21 November. Gainsborough Road from Nether Street to Nos. 10 and 12, and Netherfield Road for 40 metres from Gainsborough Road, both for 29 days from 23 October, for a footway build-out and drainage. Diversions via Nether Street, the High Road and Woodside Road (Gainsborough Road, Netherfield Road).
  • Lodge Lane and Gainsborough Road, North Finchley (N12): new no-entry rules since 29 October. Drivers can no longer enter Lodge Lane from the southern lane of Gainsborough Road, or enter Gainsborough Road’s northern lane from Lodge Lane, “to reduce cut-through traffic”. Most of Lodge Lane’s daytime yellow lines and some permit bays became “at any time” restrictions, with new resident bays outside Nos. 19 to 27, 46 to 56 and 78 (the made orders).
  • Mayfield Avenue, North Finchley (N12): closed to about 7 November. From the High Road to outside No. 2, 19 days from 19 October, while a crane removes cladding from 886 to 902 High Road. Residents keep access. Neighbouring Friern Watch Avenue’s 19-day order for the same job ran to about Saturday 31 October (Mayfield Avenue).
  • Oakleigh Gardens, Whetstone (N20): closed to about 8 November. 25 metres, 13 days from 26 October, for a BT duct connection; diversion via Athenaeum Road (the order).
  • Lanacre Avenue, Colindale (NW9): no waiting or loading to about 6 November. Both sides between Quakers Course and Five Acre, 16 days from 22 October, for street cleansing, maintenance and road markings. On 15 October this was only an intention; the council has since made the order (the made order).
  • Claremont Road, Cricklewood (NW2): closed to about 1 November. 23 metres south-east of Somerton Road, eight days from 24 October, for water chamber repairs; diversion via The Vale, Hendon Way and Cricklewood Lane (the order).
  • Meadway, Hampstead Garden Suburb (NW11): no waiting or loading until about 30 November, between Heathgate and Bigwood Road, while a burst water main is repaired. The road looks open, which is why this one catches people out (the order).
  • Queenswell School Street, Whetstone (N20): in force since Monday 5 October. Motor vehicles without a permit cannot enter Orchard Avenue, Queens Avenue, Greenside Close and Sweets Way (from Lovegrove Way to the junior school entrance) from 8.30am to 9.15am and 3pm to 3.45pm, Monday to Friday. The order is experimental, so objections can be sent within six months to highwayscorrespondence@barnet.gov.uk quoting TMO 2026_60 (the made order).
  • Deansway and Edmunds Walk, East Finchley (N2): 20mph since 9 October. Deansway is 20mph between East End Road and The Bishops Avenue, and Edmunds Walk along its whole length. Double yellow lines outside and opposite No. 50 Deansway make way for a new pedestrian crossing (the made orders).
  • Brampton Lane, Foster Street, Short Street, Cowley Place and New Brent Street, Hendon (NW4): “at any time” waiting restrictions from 15 October, for about 13 months, “to maintain traffic flow, deter obstruction and maintain public safety” (the made order).
  • Barnfield Road, Burnt Oak (HA8): one-way system suspended for 474 days from 31 August, for the step-free upgrade at Burnt Oak station. Residents keep access. The portal’s summary gives an end of 18 December 2026, but 474 days from 31 August reaches December 2027 (the made order; our report).
  • Deansbrook Road, Edgware (HA8): south-eastern footpath closed between Deansbrook Road and Barnfield Road, estimated to 27 November 2027 (the order).
  • Moxon Street, Victors Way and Whitings Road, High Barnet (EN5): parking changed for more than a year. Moxon Street’s paid bays beside 98 High Street and its loading bay are suspended, with a single yellow line instead, for 479 days from 13 September; Victors Way has six Zone C resident bays for the same period, both to about 5 January 2028; Whitings Road has lost shared and resident bays opposite and outside Nos. 37 to 47 for 409 days from 21 September (Moxon Street, Victors Way, Whitings Road).

The next fortnight

Barnet Council published new batches of notices on 22 and 29 October, each read in full on 31 October. “Order made” means the council has decided; “intention” means it has only said it intends to. The Hendon M1 closures are listed above.

Date Road What happens Diversion
Mon 2 Nov, nights Sunny Gardens, Chatsworth Avenue, Ashley Lane, Downage, Westside NW4 Closed at Great North Way, 10pm to 5.30am, M1 investigation works. Orders made See the table above
Mon 2 Nov, 1 day Colin Crescent NW4 footpath North-eastern footpath closed between Colin Crescent and Endersleigh Gardens. Order made On foot via Endersleigh Gardens, Grove Gardens, Colindeep Lane
Wed 4 Nov, permanent Ensemble Road and Albert Road EN4, New Barnet Experimental “at any time” no waiting and no loading, in place since 22 August 2025, made permanent, with a short stretch of Victoria Road. Order made None needed
Sat 7 Nov, 1 day Heronsgate HA8, Edgware Closed for 50 metres south-west from Edgwarebury Lane, traffic management safety works. Fallback date Sat 14 Nov. Order made Not given
Mon 9 Nov, 10 days Queens Parade Close N11, Friern Barnet Closed between Colney Hatch Lane and Hollyfield Avenue, substation roof replacement, to about 19 November. Order made Colney Hatch Lane, Friern Barnet Road and Hollyfield Avenue
Mon 9 Nov, 5 days Sebright Road EN5, High Barnet Closed for 20 metres north-west from Alston Road, electrical works. Intention Not given
Mon 9 Nov, 85 days Clayton Field NW9, Colindale Closed between Linklea Close and Highlea Close, water upgrade works, to about 2 February 2027. Intention Lanacre Avenue, Grahame Park Way and Field Mead
Wed 11 Nov Chesterfield Road EN5 Closed between Sellwood Drive and Stanhope Road for the second of two days of telecoms works. Order made Southbound Whitings Road, Nupton Drive, Mays Lane; northbound Mays Lane, Nupton Drive, Stanhope Road
Sat 14 Nov, 21 days Hadley Highstone EN5, north of High Barnet Closed between Kitts End Road and Dury Road, water main renewal, to about 5 December. Intention Kitts End Road, Great North Road, Barnet Road, Dancers Hill Road

The made order for Queens Parade Close spells the road “Coney Hatch Lane”; the council’s earlier notice of intention has Colney Hatch Lane, the road’s real name.

The Hadley Highstone closure is the longest new one on the list after Clayton Field. It is only an intention so far; we will add the made order when the council publishes it.

Two more made orders change parking:

  • Amendment No.322, in force since 28 October, adds “at any time” yellow lines at junctions across the borough, including Park View Crescent and Oakleigh Road South (N20), East Walk and West Walk at Uplands Road and Osidge Lane (EN4, N14), Bell Lane at Green Walk (NW4), Woodhouse Road at Lewes Road and Short Way (N12) and around Lynford Gardens, Kenilworth Road and Fairmead Crescent (HA8). Greyhound Hill NW4 by Nos. 54 to 56 loses its weekday and event-day restriction for an “at any time” one, and Ambrose Avenue NW11 gains a resident bay by 198 Golders Green Road (the made order).
  • Colindale: the council has made an order stopping up highway at or next to the A5 Hyde Estate Road, NW9 6JX, for the development approved under 19/4661/FUL. The notice does not describe the exact land. Any challenge goes to the High Court within six weeks of 22 October (the made order).

Just over the border, in Hertfordshire

Hertfordshire County Council intends to close 438 metres of the A411 Barnet Lane in Borehamwood, south-east from the Furzehill Road and Farriers Way roundabout, from Monday 2 November, for works scheduled to take seven days, and only on the days and times signed on site. Its diversion is long: through Elstree, the A5 Brockley Hill and the A41 Barnet Way (the notice, re-read 31 October).

Packhorse Lane at Ridge in Hertsmere, about three miles north of High Barnet, is under a notice to shut to all traffic except access from 7 October, for 1,203 metres from the B556 St Albans Road to Mimms Lane, for works scheduled to take six months. The county says there is no alternative route. The notice is an intention, and applies only on the days and times signed on site (the notice).

Lullington Garth: the closures have ended

Barnet Council’s order for Lullington Garth, Sussex Ring and Argyle Road in Woodside Park (N12) allowed daytime closures for carriageway reconstruction and resurfacing from 11 September, with the last stretches given until 12 October “or until works have been completed” (the order). None of the Barnet notices published since, up to 29 October, mentions Lullington Garth or Sussex Ring. If you find cones there now, it is likely to be a utility dig: search the street on LondonWorks.

Lullington Garth in Borehamwood (WD6) is a different road. It was on the signed diversion for Hertfordshire’s five-day closures of Furzehill Road, Milton Drive and Tennison Avenue from 26 October (the notice).

Parking changes in force, and the consultations that have closed

In force since 21 October: new “at any time” yellow lines at the junction of Tretawn Gardens and Marsh Lane, Mill Hill (NW7), to stop obstructive parking (Amendment No.321) (the made order).

Made on 8 October: Amendments No.320 and No.217 swap permit bays for yellow lines outside addresses getting new dropped kerbs, including West Heath Drive NW11, Finchley Road NW2, Torrington Park N12, Orange Hill Road HA8 and Watling Avenue HA8 (the made order).

In force since 1 October: Amendment No.317 and Amendment No.214 added “at any time” yellow lines at junctions and bends including Edgwarebury Lane and Parkside Drive (HA8), Hale Lane near Priory Field Drive and Highview Avenue (HA8), Brunswick Park Gardens and Brunswick Park Road (N11), Oakleigh Road North near Oakleigh Park North (N20), Victoria Road, Mansfield Avenue and Cat Hill (EN4), Childs Way (NW11), Stockton Gardens (NW7) and Albion Avenue (N10) (the made order). Amendments No.316 and No.213 did the same at junctions in HA8, NW7, N11, N2, EN5, EN4 and NW11 from 24 September, with new bus stop clearways on Potter’s Road EN5, East Barnet Road EN4, Athenaeum Road N20 and The Ridgeway NW7 (the made order). These two September and October orders were read in full when published and have not been re-read since.

Closed for comment around 15 October: SCR730 (removing five on-street EV charging bays, three of them on Grahame Park Way NW9; our report), SCR734 (23 new disabled bays), SCR735 (dropped kerbs and six bicycle hangars) and SCR736 (yellow lines on Long Lane N2 and around Broadhurst Avenue HA8). None of the orders made on 22 or 29 October carries those references, so the decisions are still to come.

Apex Corner: what we cannot stand up today

A TfL order made with Barnet Council authorised phased overnight resurfacing at Apex Corner (Northway Circus), where the A1 meets the A41, from 26 January 2026 to 25 July 2027, 10pm to 5am. Both Public Notice Portal entries for it have rolled off the site, so we could not re-check those terms against a live source. TfL’s feed listed nothing at Apex Corner on 31 October. If a closure there affects you, check TfL’s traffic status page.

The motorways: M1 slip at Hendon, A1(M) and M25 nights

National Highways’ closure report for Friday 30 October to Thursday 5 November, read per night from its spreadsheet on 31 October, books these near Barnet:

  • A1 Great North Way entry slip to the M1 northbound, junction 2: closed on Monday 2, Tuesday 3 and Wednesday 4 November, 10pm to 5.30am, for carriageway repairs. Nothing else is booked on the M1 between Staples Corner and junction 5.
  • A1(M) junctions 2 to 4: northbound junction 3 to junction 4 and southbound junction 4 to junction 2, carriageway and slip roads closed every night from Monday 2 to Thursday 5 November, 10pm to 5.30am, for tunnel maintenance.
  • M25 clockwise, junction 25 to junction 26: closed every night from Monday 2 to Thursday 5 November, 10pm to 5.30am, for tunnel works.
  • M25 anticlockwise: the junction 24 exit and entry slips closed on Tuesday 3 November, the junction 23 (South Mimms) exit slip on Wednesday 4 November, and the carriageway from junction 22 to junction 21A on Thursday 5 November, each 10pm to 5.30am.

Source: National Highways closure report.

Trains and the Tube

Burnt Oak station is closed until Sunday 8 November, and Northern line trains do not stop there; TfL says to use local buses. TfL’s planned closures list, correct at Monday 26 October, has no other closure on Barnet’s Northern line stations in the next fortnight. On Saturday 14 November there is no Night Tube between Morden and East Finchley and Golders Green (TfL planned closures).

On the main lines, National Rail lists one job in the next fortnight that touches Barnet’s Great Northern stations. After about 11.50pm on Saturday 14 November buses replace trains north of Potters Bar, and before about 7.50am on Sunday 15 November Potters Bar trains start from Alexandra Palace, with non-stop buses between Finsbury Park and Alexandra Palace. The notice does not name New Southgate, Oakleigh Park, New Barnet or Hadley Wood, so check the journey planner for those stations (the notice).

The Potters Bar works from the last train on Saturday 31 October to about 8.20am on Sunday 1 November only affected the line north of Potters Bar (the notice). We found no Thameslink notice for Mill Hill Broadway, Hendon or Cricklewood up to 14 November in National Rail’s planned incidents sitemap.

The three trackers that stay current

Roadworks pages date fast. These do not.

  1. TfL traffic status: live disruption on the red routes (A1, A41, A5, A406), organised by corridor with dates and severity.
  2. LondonWorks: TfL’s register of every proposed and current streetwork in Greater London. Search by postcode, street or the borough of Barnet, up to three months ahead. This is the one that catches the gas board digging up your own street.
  3. Barnet TraffWeb: the council’s own live map of traffic orders, consultations, collision data and parking suspensions. Barely anyone knows it exists, and it is the definitive record of restrictions on council roads.

The council also publishes a street works and road closures page. For the statutory orders themselves, which carry the exact extent, hours and diversion of every closure, search Barnet on the Public Notice Portal. That is where the closures above come from.

What we could not confirm today

  • barnet.gov.uk returned a bot-detection page when last tried on 16 October and was not re-tried today, so the council’s own street works listing has not been read. It is linked above unquoted, and nothing on this page rests on it.
  • When the Brent Cross contraflow starts and ends. TfL’s live feed says 3 November, its travel advice still says 29 October, and the feed’s “Friday 30 November” end date does not exist this year.
  • Whether the Hendon Way closures on 29 and 30 October went ahead, and which buses divert on the November closure nights.
  • Sebright Road, Clayton Field and Hadley Highstone are still intentions, as marked in the table; we will update them when the orders are made.
  • Whether the Hendon M1 investigation and the National Highways slip road closure are one job. The two sources describe them differently.
  • Whether Friern Watch Avenue and Claremont Road reopened on time. Their orders end on 31 October and 1 November “or until works have been completed”, and we have not seen either road.
  • Apex Corner, as set out above: the order’s end date could not be re-checked against a live source.

Who runs which road, and where to report a pothole

Two authorities share Barnet’s roads, and a report to the wrong one goes nowhere. TfL manages the red routes, which it says make up 5% of London’s roads but carry up to 30% of its traffic. In Barnet that means the A1 (Watford Way and Barnet Way), the A41, the A5 and the A406. Defects on those go to TfL Streetcare or 0343 222 1234.

Everything else is Barnet Council’s, from the A1000 through Whetstone and High Barnet down to your own street. Report those through barnet.gov.uk or FixMyStreet.

Diagram of who runs which Barnet roads: TfL red routes are the A1 Watford Way and Barnet Way, the A41, the A5 Edgware Road and the A406 North Circular, reported via TfL Streetcare; Barnet Council runs everything else including the A1000, reported via the council or FixMyStreet

The council side is mid-way through a heavy investment cycle. Barnet approved a £15.52 million highways programme for 2026/27 in December 2025, £9 million of it on roads and £3.4 million on pavements. That is part of a £97 million package announced in 2024 for its 723 km of roads and 1,290 km of pavements, and the council says it repaired nearly 4,000 potholes in 2025 (Highways News, March 2026).

Station parking, for the park-and-ride commute

Tariffs below were re-checked on 13 September 2026 and are unchanged.

  • High Barnet station: 173-space surface car park run by Saba for TfL, open 24/7, cashless with ANPR. £11 a weekday, £6.30 at weekends, £54 a week, £216 a month, £648 a quarter, £2,592 a year. Motorcycles £2. Bank holidays are charged at the weekday rate. Six of the 173 spaces are blue badge bays. Blue Badge holders park free in a designated bay, but you have to register the stay at a machine on arrival, and standard rates apply if those bays are full.
  • Mill Hill Broadway station: 42-space car park run by APCOA for Thameslink. £11.10 a weekday, dropping to £8.10 after 10am and £3.60 after 5pm, £4.10 at weekends. Season tickets are £45.10 a week, £169.70 a month, £444.70 a quarter and £1,455.90 a year, with a premier ticket at £1,742. Blue Badge holders park free. A 15p convenience fee applies to every tariff, and daily rates expire at 4am.
  • Edgware station: no operator tariff page was published when we checked. The nearest confirmed TfL car park is Canons Park, one stop away with 161 spaces.

If you are parking on-street instead, the borough’s controlled zones and charges are covered in our parking in Barnet page, and if the roads are against you the trains usually are not.

What it means for you

If you drive through Brent Cross, allow extra time every day, not just on closure nights. The flyover is one lane each way in the contraflow, which TfL lists to 20 November. TfL’s advice, if you do not need to stop at Brent Cross, Staples Corner or Henlys Corner, is to go another way.

If you live off Great North Way in Hendon, Sunny Gardens and Chatsworth Avenue shut at the A1 end every night from Monday 2 November for 13 nights, and Ashley Lane, Downage and Westside for three nights, 10pm to 5.30am.

If you drive to Arkley or Borehamwood, the A411 Barnet Road closure at Glebe Lane, listed to 5 November, is no longer on TfL’s feed, though TfL has not confirmed it has reopened, and Hertfordshire plans to shut part of the A411 Barnet Lane in Borehamwood from 2 November.

If you head north on the A1(M) or round the M25 late, the A1(M) between junctions 2 and 4 and the clockwise M25 from junction 25 to 26 are shut every night from Monday to Thursday.

If you live off the High Road in North Finchley, Mayfield Avenue is shut to about 7 November, and Lodge Lane now has no-entry rules at Gainsborough Road.

If you use the Tube at Burnt Oak, the station is closed to Sunday 8 November.

Frequently asked questions

Is the Brent Cross flyover closed?

Northbound, yes, for now. TfL’s feed on 31 October says northbound traffic leaves and rejoins at Brent Cross Interchange and southbound is down to one lane. From 7am on Tuesday 3 November a contraflow runs on the A41 Hendon Way, one lane each way. Hendon Way closes completely overnight, 10pm to 5am, on 19 and 20 November.

When is the A406 closed at Brent Cross?

Lane one of the westbound A406 is shut from Golders Green Road until 5am on Friday 13 November. The westbound A406 closes fully between the interchange slip roads on the nights of 12 and 13 November, with traffic sent up and over the interchange. TfL then plans five more nights beneath the interchange, both directions, between 6 and 12 January 2027.

How long will the Brent Cross roadworks last?

TfL says the flyover renewal will take up to two years. This autumn’s lane restrictions are listed to 20 November, then the works pause from late November 2026 to early January 2027.

Is Lullington Garth still closed?

Not under the council’s order. The phased daytime closures of Lullington Garth, Sussex Ring and Argyle Road in Woodside Park ran from 11 September to 12 October, and no new order for the road has been published since. The Lullington Garth in Borehamwood is a separate road.

Are there roadworks at Staples Corner?

National Highways’ report to 5 November has no closures on the M1 from Staples Corner to junction 5, but the A1 Great North Way entry slip onto the M1 northbound at junction 2 is shut on the nights of 2, 3 and 4 November. TfL advises drivers who only pass through Brent Cross, Staples Corner or Henlys Corner to find another route while the flyover works run.

Are buses affected by the Brent Cross works?

Buses still serve Brent Cross but run slower. TfL says some routes divert during the overnight Hendon Way closures and some stops on or near Hendon Way are not served, but has not named the routes for the November nights. The Brent Cross footbridge is closed for repairs.

Sources

TfL, Barnet Council’s statutory orders, National Highways, TfL’s planned closures and National Rail re-checked on 31 October 2026. Individual closures change weekly, so confirm on the linked trackers before you travel. Related: parking in Barnet, Barnet train times to London and Barnet bin collection days.